Panama Canal Expansion Update

Beginning 2013, the Expansion Program has completed several projects
By Patrick Burnson, Executive Editor
February 11, 2013 - SCMR Editorial

As U.S. supply chain managers continue to monitor a possible modal shift in the years ahead, the Panama Canal Expansion has reached several milestones.

Beginning 2013, the Expansion Program has completed several projects.

Dredging of the navigational channels has been completed. This included both Canal entrances, on the Pacific and Atlantic sides, as well as Gaillard Cut. The remaining dredging work to be done in Gatun Lake is expected to be completed this year.

The excavations of the Pacific lock access channel are 70 percent complete. This project calls for the excavation of more than 50 million cubic meters of materials along a 6.1 km span and is executed in four phases. Three of the four phases have been completed and the fourth phase is 69 percent complete.

In addition, the first shipment of 47 valves, to be used for the operation of the third set of locks, arrived during the last couple of weeks. These valves are part of the Post-Panamax locks electromechanical system that will regulate water flow between the chambers, the culverts and water-saving basin conduit. A second shipment is scheduled to arrive at the end of January. By the end of 2013, a total of 158 valves (culvert, equalization and conduit), 84 bulkheads and 328 trash racks will have arrived for the project. The valves where built in South Korea by Hyundai Samho Heavy Industries

Construction of the new locks has a 37 percent progress. The new lock complexes in the Pacific and Atlantic sides will feature three chambers, three water-saving basins per chamber, a lateral filling and emptying system and rolling gates.

“We estimate based on the progress that we can begin commercial transits mid-2015,” said the Panama Canal Administrator.

Supply chain managers should be relieved that the Panama Canal Authority is also closely monitoring progress on every component of the Expansion Program to guarantee that contractors comply with the quality required by each contract.

The Panama Canal Expansion Program will be the largest project at the Canal since its original construction and will double its capacity to allow more traffic.



About the Author

image
Patrick Burnson
Executive Editor
Patrick Burnson is executive editor for Logistics Management and Supply Chain Management Review magazines and web sites. Patrick is a widely-published writer and editor who has spent most of his career covering international trade, global logistics, and supply chain management. He lives and works in San Francisco, providing readers with a Pacific Rim perspective on industry trends and forecasts. You can reach him directly at .(JavaScript must be enabled to view this email address).

Subscribe to Logistics Management magazine

Subscribe today. It's FREE!
Get timely insider information that you can use to better manage your
entire logistics operation.
Start your FREE subscription today!

Recent Entries

Seasonally-adjusted (SA) for-hire truck tonnage in March was up 1.1 percent on the heels of a revised 2.8 percent (from 3.1 percent) February decline, with the SA index at 133.5 (2000=100). This is off 0.3 percent from the all-time high for the SA of 135.8 from January 2015 and is up 5 percent annually.

Intermodal volume was up 8.1 percent annually at 280,016 containers and trailers. This outpaced the week ending April 11 at 270,463 and the week ending April 4 at 271,127. AAR said this tally marks the second highest weekly output it has ever recorded as well as the first time container and trailer traffic was higher than carloads for a one-week period.

Ocean cargo carrier service reliability across the three core East-West trades hit a five-month peak in March with an aggregate on-time performance of 64 percent, according to Carrier Performance Insight, the online schedule reliability tool provided by Drewry Supply Chain Advisors.

The Airforwarders Association, which represents more than 360 companies that move air cargo through the supply chain, today applauded an agreement reached by Congressional leaders to advance legislation giving the President authority to conclude key global trade agreements.

Despite great opportunity for growth, the logistics market in Latin America is lagging behind other emerging markets thanks in part to its notoriety for corruption, violence, poor infrastructure and government bureaucracy.

Article Topics

Blogs · 3PL · Supply Chain · Management · All topics

About the Author

Patrick Burnson, Executive Editor
Patrick Burnson is executive editor for Logistics Management and Supply Chain Management Review. Patrick covers international trade, global logistics, and supply chain management. He lives and works in San Francisco, providing readers with a Pacific Rim perspective on industry trends and forecasts. Contact Patrick Burnson

Comments

Post a comment
Commenting is not available in this channel entry.